| Day 40: Today the crew from "TK Danis Poured Foundations" came to set up all the
      forms for the stem walls. The footing for the left wall of the garage was
      not in the right place so they had to order a concrete delivery for the
      early afternoon.  They poured the footing for the lolly columns at the
      same time. They will need to come Monday, June 10th,  to finish setting
      up the forms. Pouring the walls is scheduled for Tuesday, June 11th. I made two time lapse videos again, one for the North Camera and one for the South Camera. I merged in a couple clips of sped up real time video to give a closer look at some of the activities. |