| Day 79: The framing effort today concentrated on finishing the gable roof
      that runs front to back over the addition and the old kitchen and living room.
      Work also started on replacing the existing roof. The plywood used back in 
      1968 was only 3/8" thick and was very spongy to walk on. We decided that it
      was worth the extra $2k to replace all the plywood with 5/8" brown Advantech.
      That effort started today. |